April:
| Sunday | Monday | Tuesday | Wednesday | Thursday | Friday | Saturday |
| 1. | 2. | 3. | 4. |
5. Integrate Profium Package and output proper XML file
input.
Complete edge text patch. |
||
| 6. | 7. | 8. Test different graph layout packages. | 9. Use test RDF to construct simple graphs. | 10. | 11. | 12. |
| 13. | 14. | 15. | 16. | 17. | 18. | 19. Begin incorporating actual instance data ontology to build working TouchGraph. |
| 20. | 21. | 22. | 23. Integrate new TouchGraph Layout package for edge hints as Applet. | 24. | 25. | 26. Planned completion of intermediary package. |
| 27. Debugging and final deployment of project. | 28. | 29. | 30. |
May:
| Sunday | Monday | Tuesday | Wednesday | Thursday | Friday | Saturday |
| 1. Updating Website and Finalizing Project Files | 2. | 3. | ||||
| 4. | 5. Project Final Presentation | 6. | 7. | 8. | ||