Project Schedule

April:

Sunday Monday Tuesday Wednesday Thursday Friday Saturday
    1. 2. 3. 4. 5. Integrate Profium Package and output proper XML file input.

Complete edge text patch.

6. 7. 8. Test different graph layout packages. 9. Use test RDF to construct simple graphs. 10. 11. 12.
13. 14. 15. 16. 17. 18. 19. Begin incorporating actual instance data ontology to build working TouchGraph.
20. 21. 22. 23. Integrate new TouchGraph Layout package for edge hints as Applet. 24. 25. 26.  Planned completion of intermediary package.
27. Debugging and final deployment of project. 28. 29. 30.      

May:

Sunday Monday Tuesday Wednesday Thursday Friday Saturday
        1. Updating Website and Finalizing Project Files 2. 3.
4. 5. Project Final Presentation 6. 7. 8.